[Construction Manual] CPB 12-1, "Use of "Other Days""

Construction Publications construction_publications at dot.ca.gov
Thu Feb 23 07:24:12 PST 2012


Dear Construction Subscriber,

This bulletin explains that "Other day" time extensions are no longer
allowed due to specification changes. Days worked during the contract are
either a working day or a nonworking day and the form CEM-2701, "Weekly
Statement of Working Days" has been revised to eliminate the column for
entering "Other day" time extensions. All time adjustments require a change
order.

We have posted it and its attachment on our construction website:

		 http://www.dot.ca.gov/hq/construc/manual2001/CPBindex.HTM